This 45,000 project consisted of constructing a new multi-story
sanctuary as well as a total renovation of the existing building.
The new
addition
involved excavation, rock removal, shoring & underpinning the existing
structure while occupied. A new multi-story elevator and handicapped
access ramp was installed as well as new electrical, water, sewer
and gas services.
Mechanical upgrades included the installation of two
75
ton roof mounted chillers and sound enclosures, two dual fuel
boilers and all related piping, sheetmetal work and controls to service
the entire facility.

|